|
(BERNARD
MAHUNG |
PLAINTIFF |
BETWEEN |
(
(AND
(
|
|
|
(KARL
BURKE |
DEFENDANT |
Supreme
Court
Action No. 107 of 1978
15th July 1982
Moe, CJ
Mr. Denys
Barrow for the Plaintiff
Mr. Wilfred Elrington for the Defendant
Contract
- Breach of Contract - Repudiation of agreement - Damages
- Evidence - Question of fact - Failure to complete contract
within a reasonable time is not repudiation - Time was not
of essence of the contract - Claim for breach of contract
fails.
J
U D G M E N T
On July
7th 1977 the plaintiff and defendant entered into an agreement
as follows: -
"The
following is to certify that agreement has this day July
7th 1977 been reached between Mr. Bernard Mahung (owner)
on the one hand and Karl Burke (contractor) on the other
to erect an upper flat building on existing building size
being 24 x 32 inside measurement; structure to be of reinforced
concrete and 8 x 8 x 16 concrete blocks according to plan
submitted with agreed alteration complete with septic and
painting. Owner to supply all required materials on site
and contractor responsible for materials supplied and labour.
"The
agreed cost of labour is FOUR THOUSAND FIVE HUNDRED DOLLARS
($4,500.00) Belize currency, same amount to be paid as follows:
Advance (as the law specifies) the amount of seven hundred
dollars; then on the Friday of the third week after commencement
Two hundred and fifty dollars, thereafter, as requested
by contractor taking into consideration the amount of production."
The plaintiff
claims that the defendant proceeded to erect the four walls
and roof for the upper flat but on the 27th February 1978
ceased to do any further work and thereby repudiated the above
agreement which repudiation the plaintiff accepted by letter
dated 16th May, 1978. He also claims that the defendant failed
to apply certain materials to the said agreement, has not
returned them and has lost his building plan. He now seeks
damages for the expense incurred in employing another builder
to complete the building and for the inconvenience, trouble
and loss he has suffered. The defendant denied that he repudiated
the contract and avers that he was prevented by the plaintiff
from completing the work. He also denied failure to apply
the materials as alleged.
The evidence
is that work under the agreement commenced about the 15th
July 1977 i.e. about one week after the agreement was signed.
The plaintiff says work stopped on 27th February 1978 whereas
the defendant maintained that he worked on the building until
May 1978. On this aspect of the matter I found the defendant's
account more reliable. He gave the impression that he recalled
events quite clearly and his evidence on this was more specific
and definite than the plaintiff. On the other hand the plaintiff
did not appear to be clear as to what transpired in this regard.
His demeanour suggested that he was either not recalling exactly
what transpired or was reluctant to cede that the defendant
was in fact still working on the building beyond the period
he had pleaded. And there is evidence to which I refer in
more detail shortly that a misunderstanding about the erection
of the building had been going on until about May 18th when
the plaintiff changed the locks on the doors to the building
at which time the defendant's tools were still in the building.
I accepted the defendant's evidence that he was still working
on the building as at May 9th, 1978.
I found
that before that date i.e. 9th May 1978, there had arisen
some dispute between the parties about the erection of the
building. The plaintiff approached the defendant on more than
one occasion about finishing the building. He couldn't recall
how many times he did so no what defendant replied but said
merely that the defendant's response seemed unfavourable.
By a personal letter dated 16th May 1978 the plaintiff gave
the defendant one week within which to come to an amicable
solution about the misunderstanding concerning the erection
of the house failing which he would take legal action. In
response thereto, the defendant told the plaintiff that it
had been his desire to do so since November 1977 and was still
anxious to do so whereas the plaintiff had chosen to resort
to "slander, intimidation, verbal abuse, defamatory remarks
and threats." Before he had received this letter from
the plaintiff, the defendant has consulted a lawyer who on
the said 16th May wrote to the plaintiff stating "Mr.
Burke has informed me that because he was unable to conclude
the construction of a house he had undertaken to build for
you, you have deliberately embarked on a campaign to besmirch
has character." The plaintiff's lawyer also in a letter
dated May 16th to the defendant stated that from July 1977
to that date was more than a reasonable time within which
to complete the contract. That because of the defendant's
excessive delay and obvious repudiation of the contract, the
plaintiff was entitled to treat the contract as at an end.
He also forbade the defendant from going on the premises for
any purpose whatever and demanded a return of the house keys.
I turn
now to determine whether the defendant can be held to be in
breach of the contract. There was not time stipulated in the
agreement for completion of the contract. Agreement to complete
within a reasonable time is therefore to be inferred. What
was a reasonable time is a question of fact for my decision.
This was a difficult decision to make. There was little to
go on as to the time to be regarded as normal within which
to build such a structure in Belize. There was evidence from
the defendant that if he could have finished about two months
after January 1978, i.e. about end of March or about 8 months
for the job. There was evidence from the plaintiff which suggests
the other building contractor took from about mid November
1978 to mid March 1979 about 4 months to finish what was left
to be done. If I were to base my judgment on what I have seen
in Belize, taking 10 months i.e. from July 1977 to May 1978
to erect the structure is not necessarily unreasonable and
the portion of evidence just referred to tends to confirm
this. In this case I have to take into account that the structure
was to be reinforced concrete and cement blocks but there
was no water on the site which thus necessitated spending
much time daily in drawing if from elsewhere and putting it
in a container before certain work could be done. There is
no evidence that water was ever run on to the site during
the time the defendant was working on the building. Further
the defendant when he needed materials had to seek transportation
and along with his employees collect the materials from the
plaintiff's mother's residence and bring them to the site.
I also took into account that the amount paid for the labour
was extremely low. This would certainly have a bearing on
the amount of workers employed and consequently the speed
of production. The plaintiff's own witness, a contractor whom
he employed to finish the work after he had shut out the defendant
said that at the relevant time if he had been given the job
from start he would have charged thirteen to fourteen thousand
dollars. He said it was not reasonable to build such a house
for $4,500 and it would be very hard to build it for that
amount. Indeed the witness charged $7,300 to finish the work
and with that added to the $4,500 paid as the defendant's
agreement called for, the plaintiff still got his building
for about a quarter less than what should have been properly
charged from the start. The plaintiff could not reasonably
expect for $4,500 the result i.e. the production for which
he should have paid $14,000.00. The plaintiff was getting
a job "dirt cheap" from the defendant and the defendant
was labouring under trying circumstances. The bargain doesn't
appear to have been fair and reasonable. Taking all the above
factors into account I would hold that as at 16th May 1978
the defendant being still at work on the building was not
unreasonable, and thus was not in breach of this contract.
I however
do not rest there. Even if I am wrong and the defendant as
at May 16th 1978 had in fact exceeded what may be properly
regarded as a reasonable time within which he ought to have
finished the building and was thereby guilty of delay, the
question which then arises is whether the defendant can be
held to have thereby repudiated the contract or was guilty
of a breach entitling the plaintiff to treat the contract
as at an end.
In Cheshire
& Fifoot on Contract (4th edition) at p. 485, it is stated
"A breach of contract is a cause of discharge only if
its effect is to render it purposeless for the innocent party
to proceed further with performance. Further performance is
rendered purposeless if on party, either shows an intention
no longer to be bound by the contract or breaks some stipulation
so essential to the continuance of the contractual tie that
the very foundation of the contract is discharged." and
at p. 486 "Repudiation of a contract is a serious matter,
not to be lightly found or inferred" and it is pointed
out that the question whether the inference is justified is
one of fact dependent upon the nature of the default and the
circumstances in which it was made.
I do not
think that an intention by the defendant to repudiate the
contract could be inferred from his failure to complete within
a reasonable time. The evidence which I accepted is that the
defendant was trying valiantly to keep his part of the bargain.
By November 1977 the defendant has used up $4,450.00 and sought
loans from the plaintiff to assist him in completing the job.
He only raised $300.00. When the money ran out, he lessened
his work force, worked on the building three days a week and
two elsewhere or 2 on the building and 3 elsewhere to keep
things going and eventually worked on it by himself. But although
there is not intention to repudiate a contract, it is still
discharged if the breach is so fundamental as to destroy the
foundation of the contract. Did the defendant's failure to
complete the building within a reasonable time go to the root
of the contract? In this case, time was not of the essence
of the contract and therefore non-completion of the contract
by the defendant within a reasonable time did not release
the plaintiff from the contract.
In the
circumstances I think the right of the plaintiff would be
as stated by Singleton L.J. in Charles Rickards Ltd., v.
Oppenheim [1950] 1 A.E.R. 420. He said "If a person
wants something done and that which he has contracted to have
done is not done within a reasonable time ---- he has the
right in the circumstances to say "Well, I will not have
unless you deliver it within a certain length of time"
and states a reasonable time". What was necessary after
the reasonable period for completion had expired was letter
to the defendant stating that from thereon time was being
regarded by the plaintiff as essential to the contract and
giving the defendant a reasonable time within which to comply.
Rather than that what was sent to the defendant was letter
treating the contract at an end and prohibiting the defendant
from doing any further work on the house. As Harman J.
said in Smith v. Hamilton [1950] 2 A.E.R. at p. 933,
"If time to be not initially of the essence of the contract,
one party cannot, by his own motion, make it so."
In the
result I would not find that the defendant repudiated the
contract or was guilty of a breach entitling the plaintiff
to regard the contract between them as at an end. The plaintiff's
claim for damages for repudiation and breach of contract fails.
I am not
satisfied that the defendant lost the plan nor that he is
to be blamed for the absence of a length of galvanized pipe,
part of the materials claimed to be lost. The defendant has
admitted he has fluorescent light value $16.00 belonging to
the plaintiff. He is to pay the plaintiff for it. Judgment
accordingly. Defendant to have his costs.
-------------OO------------
|