|
(OLMEC
EQUIPMENT LTD.
( |
PLAINTIFF |
BETWEEN |
(AND
( |
|
|
(O.
SEAWELL |
DEFENDANT |
Supreme
Court
Action No. 102 of 1980
22nd July 1982
Rajasingham, J., Q.C.
Breach
of contract - Waiver by Plaintiff of prepayment of advance
but Defendant failing to pay advance - Defendant also failing
to pay for hire of tractor and lowboy under same contract
- Contract lawfully terminated by Plaintiff.
J U D G M E N T
The Plaintiff
claims a sum of $4,647.64 for the hire and transport of a
D7 tractor and the hire of a lowboy to the Defendant. The
Defence claims that the Plaintiff terminated the hire in breach
of his agreement with the Defendant and thus caused pecuniary
damage to the Defendant. The Defendant counterclaimed for
a sum of $5,000.00 as special damages but led no proof of
that claim.
The hire
of the two vehicles is not contested. In fact the Defendant
does not deny that a sum of $262.64 is due for the hire of
the lowboy and the gasoline supplied for it. It is the terms
of hire that have become an issue between the parties. The
Plaintiff's Managing Director, Mr. Polack, states that he
required an advance for the hire of the D7 tractor, and the
Defendant agrees that an advance was required but states that
he explained to Mr. Polack that he himself would only be paid
by Government on the contract to build a road on the basis
of work completed at the end of every two week period and
hence he, the Defendant, could not raise an advance. Curiously
enough the D7 tractor was in fact supplied without the pre-payment
of an advance. Mr. Polack explains the reason for this being
the delay in supplying the tractor owing to its having to
undergo repairs, a delay Mr. Polack says was of four weeks
duration, but which the Defendant says was nearer to three
months. However, the real matter in issue would appear to
be whether an advance was required to be paid in due course
after the hiring had commenced. Mr. Seawell himself admits
to paying an advance to the other hirer, Stedman. I am satisfied
therefore, that an advance appears to be the normal practice
unless for reasons such as acquaintance it was waived. The
parties in this Action were not so acquainted and in the circumstances
I am inclined to believe Polack when he says that all he waived
was the requirement of pre-payment. The Defendant has not,
by correspondence or even in the pleadings, challenged this
position. In fact he ignored all correspondence.
There
is no doubt that the Plaintiff's Action in withdrawing his
D7 tractor played a part in the Defendant losing his contract,
but Polack's Action was justified in view of Defendant's default
both in paying an advance and in paying the hire regularly.
It would appear that the Defendant set out to do the contract
without capital and in the expectation of paying from receipts,
but events overtook him and caused him to default.
I allow
the Plaintiff's claim of $4,647.64 with costs. I dismiss the
Defendant's counterclaim.
----------OO----------
|