|
(FRANCISCO
NUNEZ
(MIRNA NUNEZ
( |
PLAINTIFFS |
BETWEEN |
(AND
( |
|
|
(DARRELL
CLOUD
(COSME LOPEZ |
DEFENDANTS |
Supreme
Court
Action No. 120 of 1999
Shanks, J.
13th April 2000
Mr.
Elrington for the Plaintiffs.
Mr. Welch for the First Defendant.
Mr. Sooknandan for the Second Defendant.
Engineering and construction agreement for an apartment
building -
Building collapsing before completion - Apportionment of liability
-
Assessment of damages.
J U D G M E N T
This is
a claim against the designer and builder of a two storey concrete
apartment building in San Pedro. The building was started
in late 1998. In March 1999 when it was nearly complete and
paid for it suffered a major structural collapse while construction
was still going on. Neither the builder or the designer has
taken any steps to rectify the damage to the building.
The relationship
between the Plaintiffs and the two Defendants is governed
by two agreements. The first is between the Plaintiffs and
the first Defendant, Darrell Cloud. It is an agreement dated
30th July, 1998. Under this agreement Mr. Cloud is described
as the "project engineer" and is to do among other
things the following:
-
Design
an apartment building with three rental units on the ground
floor and a residential apartment for the Nunez family
on the second floor.
-
Be
the project engineer to supervise the entire project from
start to finish.
-
Make
a construction contract with the contractor to sign.
-
The
project engineer shall have full responsibility and control
of the project and shall work closely with owners and
the contractor. He shall be fully accountable to the owners
and make regular and frequent reports to them on the progress
of the project. For this work the project engineer is
to be paid a design fee if 2% of the total cost of the
project and a fee for supervision of 8% of the total cost
of the project.
The relationship
with the second Defendant, Cosme Lopez, who was the builder,
is governed by a construction agreement dated the 21st October,
1998, which was produced for the Plaintiffs by the first Defendant.
That provides that the Plaintiffs hired the second Defendant
to "build the building which is being designed for them
by Architectural Designer and Engineering Service of San Pedro
who is also being retained as project engineer for this project."
The agreement continues:
-
"The
building is two storeys with three apartments on the ground
floor and one owner's apartment on the second level as
shown on the set of plans which have been approved by
the San Pedro Planning Board and a part of this agreement.
-
The
building will be constructed according to the set of blue
prints which have been furnished to the contractor. No
changes will be made on the designer's materials without
first securing permission from the project engineer and
of the owner.
-
An
agenda sheet will then be made and deductions or additions
will be made to the labor cost differential which is reflected
by the change. The total labor cost for the construction
of this project is $56,090.00 Belizean dollars and the
construction time to complete this project is approximately
six months. An attempt will be made to complete it in
four months
." The agreement is signed by the
Plaintiffs and the second Defendant. It will be apparent
from my description of those two agreements that the first
Defendant's role was central throughout the entire process
of design and building.
The first
Defendant prepared for the Plaintiffs a bill of quantities
in respect to the whole project which shows a total cost of
$211,882.00 which includes $23,434.00 for furniture and fixtures
for the three apartments. The Plaintiff took out a loan to
raise this money at a rate of interest of 17%. He had spent
a total of $171,371.00 when the collapse happened. There was
therefore a further $17,077.00 left to pay for the building
excluding furniture and fixtures. In the immediate aftermath
of the accident the first Defendant told the Plaintiff that
the collapse had taken place because of an air pocket below
the foundations. The Plaintiff hired Dwayne Thurton to investigate
the cause of the collapse and to say who was responsible in
his view.
Mr. Thurton
prepared a clear and concise report in May, 1999. He also
gave evidence which, in spite of his relative youth, was careful
and impressive. He made some excavations and could find nothing
wrong with the rock below the building or any evidence that
the piles had sunk. He made a careful study of the contract
documents and of the evidence on site. His conclusion as to
the cause of the collapse was as follows:
"Based
on the information gathered, the most probable point of failure
initiation is the ground beam on grid (A) as a result of shear
overloading. This failure subsequently caused redistribution
of stress throughout the building and, thus, 'knock-on' failures.
These included major structural limit state failures in columns,
beams and slabs, serviceability failure in walls and other
elements and the rotation of the entire building structure.
The overloading of the beam was primarily due to the fact
that column 2x (A) was some 3 feet out of alignment and was
supported directly by the ground beam rather than a pile as
originally designed.
If the
changes from the original design with respect to the moving
of at least four
columns off alignment, particularly column 2x (A) were made
or endorsed by the project engineer, then the responsibility
is clearly his.
In construction
arrangement as the one utilized for this project, a contractor
would not normally be expected to verify structural changes
or designs made by the designer.
If, however,
the moving the columns were, in fact, construction error,
then the responsibility should be shared between the project
engineer and the contractor."
He had
also concluded in the second part of his report as follows:
"The
core of the problem rests on the fact that there were changes
made to the designs that were reflected in the construction.
The changes introduce significantly higher load intensities
in certain areas, particularly in Beam A. The changes apparently
were not accompanied by new structural details. Note that
similar changes were made in several other locations in the
building. The potential for future failure may, therefore,
still exist". There is then reference to various photographs
which he says shows inclined cracks that span across the depths
of Beam A, up and a way from its support. "These are
characteristics of shear cracks. For shear reinforcements
to be effective, they must be spaced close enough to each
other so as to intercept these cracks which are generally
about 45 degrees from the horizontal. In the cases of both
the constructed and the detailed beams, the reinforcements
are not close enough to play a significant role as cracks
are able to be formed between them."
The first
and second Defendants gave evidence. The first Defendant told
me that there had been no changes from the design and that
he had designed the building with pillars out of alignment
but that the beams were designed in accordance with the appropriate
codes and that the plans had been approved by the local authority.
Unfortunately, he did not bring his design plans to court
to make good this case. He also told me that he supervised
the construction on a day to day basis and that the building
was built in accordance with his instructions which evidence
was not surprisingly confirmed by the second Defendant. The
first Defendant's theory remains that some of the piles had
been driven into an unstable area but he recognized that he
had had no independent expert to verify this or to report
on the matter. Further, Mr. Thurton had not been asked about
the particular columns which he said had sunk during his evidence.
Faced
with that evidence I really have no choice but to accept the
views of Mr. Thurton. Whether or not the building as built
was in accordance with first Defendant's plans, the beam which
failed was clearly inadequately designed. This must be the
responsibility of the first Defendant and he must be liable
for the damage which resulted from it. On the basis of his
and the second Defendant's evidence and Mr. Thurton's views,
the second Defendant will not be liable.
I should
say that even if I accepted the first Defendant's views that
the only cause of the collapse was that the piles were driven
into an unstable area, I suspect that he would have still
been found liable. He was fully responsible for the project
under his agreement. I would have thought such responsibility
must extend to checking by whatever means necessary that the
building was going to be built on firm ground.
I turn
to damages. Mr. Thurton expressed the view that the building
was now in a "horrible state", a view confirmed
by the photographs. He said that there were so many uncertainties
about its stability that the best way to proceed would be
to demolish it and to start again. I accept that view. He
said clearing the site would cost $15,000.00 and the first
Defendant did not quarrel with that figure. He said to build
the building now would cost at least $225,000.00, a view I
accept. If the work starts now it is likely to take at least
another six months which means the Plaintiff will get his
building at least 18 months late. I accept his evidence that
he would have been able to rent the three apartments for $1,000.00
per month each and the upstairs flat for $1,500.00 per month
before moving into it with his family. He has therefore lost
rental of $4,500.00 a month for 18 months which totals $81,000.00.
He must give credit for the amount he still had to pay under
the contract with the first and second Defendants namely $17,077.00.
He is
therefore entitled to damages of $303,923.00, which is $15,000.00
+ $225,000.00 + $81,000.00 - $17,077.00. I do not award him
interest since the cost or rebuilding is prospective and the
interest on the bank loan was to have been paid off from the
rental income which is a head of damage itself. The $10,000.00
spent on Mr. Thurton's report ought be recoverable as part
of the costs in the action since that report really deals
only with the assignment of responsibility for the failure.
There
shall therefore be judgment for the plaintiff against the
first defendant for $303,923.00 and the claim against the
second Defendant shall be dismissed.
|