|
(ERIC
FLOWERS |
PLAINTIFF |
BETWEEN |
(
(AND
( |
|
|
(BATRA
(BERNE HYDRO-
(MECHANIC LTD. |
DEFENDANTS |
Supreme
Court
Action No. 210 of 1979
6th August, 1981
Moe, J.
Mr. Michael
C. Young for the Plaintiff
Mr. Derek Courtenay S.C. for the Defendant
Negligence - Duty of care owed by employer towards
employee - Employee involved in serious accident during
course of employment which made employee a
paraplegic - Assessment of damages - Applicable
principles.
J
U D G M E N T
The plaintiff
in this matter was employed by the second defendant as a labourer
at a Water Treatment Plant under construction at Mile 17 on
the Northern Highway. The second defendant, a construction
company, was engaged under a contract between it and the first
defendant, for the provision of services relating to the said
construction which the first defendant, itself an engineering
and construction contractor, was engaged in carrying out.
2. The
plaintiff alleged that on the 6th of July, 1979 at the said
plant, while in the course of his employment assisting his
fellow employees and employees of the first defendant in raising
a steel bridge for a water tank, the boom of a crane, driven
by the servant or agent of the defendants, suddenly fell and
hit him, in consequence whereof he sustained severe injuries
and suffered loss and damage. The defendants admitted these
matters.
3. The
plaintiff claims that the injuries and loss and damage were
occasioned by the negligence and/or breach of duty of the
defendants, their servants or agents, and/or the breach of
the contract of employment on the part of the second defendant,
its servants or agents.
4. The
defendants denied liability and pleaded that the matters concerned
were the result of an inevitable accident and arose notwithstanding
the exercise of all reasonable care by the defendants, their
servants and agents.
5. There
was a defendants' admission as indicated above which included
in particular that the boom of the crane suddenly fell and
hit the plaintiff. In addition, the evidence coming from both
plaintiff and defendant witnesses, was that the gantry cable,
which holds up the boom, had burst thus causing the boom to
fall. I so held.
6. Lewin
Moguel, a mechanical engineer, then employed by the second
defendant, gave evidence that he had inspected the cables
of the crane some days before the incident; that is after
it had done a job of driving piles on the same site. He noticed
defects in the cables; they were worn and frayed in certain
areas. He told the project engineer, Mr. Bill Holland what
he had observed. He however gave us his opinion that at that
time the cables were not dangerous. Alex Flowers, an equipment
operator then employed by the first defendant, said that in
his view the crane concerned was a little below par. On the
day of the incident he noticed that all the cables on the
crane were in bad shape. The cables were dry and fraying in
some areas. His observation was from a distance where the
boom was at approximately a 300 angle from the ground. He
pointed out the defects to the operator of the crane.
7. The
project manger employed by the first defendant, Mr. Bill Holland
gave evidence that the crane was hired from one Larry Cain
of Frontier Developments Corporation. According to Mr. Cain,
the crane was bought second hand by his company and they owned
it for about 12 years at July, 1979. A new boom cable was
placed on the crane in May, 1979 and when the crane was hired
to the first defendant it had worked some fifty-three hours.
Lennox Gibson, the crane operator, also said that the boom
cable concerned was on the crane from about May, 1979. On
the day before the incident, the boom was extended by some
57 feet. Mr. Holland denied being told about the condition
of the cables by Mr. Moguel and Mr. Gibson denied being spoken
to by Alex Flowers about the cables. Again Mr. Bernier, a
technical mechanic employed by the second defendant, while
stating that he did not observe the cables on the crane, said
that his general impression of the equipment on the crane
was that it was relatively old.
8. Lastly
Mr. Michael Belle, a consultant mechanical engineer gave his
view that the cable as exhibited in Court frayed by normal
wear and tear. The amount of fraying would have reduced the
capacity by 10 -15%. He further gave opinion that the cable
had worked for a couple of hundred hours. He stated that the
cable broke on account of one of two reasons; either because
of a pinch or because of a kink. In his opinion, because of
areas of the cable which appear to be flattened down, the
cable broke because of a pinch. This occurs where a cable
lays over itself and prevents its movement.
9. I found
that the boom cable was in fraying and deteriorating condition.
I also accepted the evidence of Michael Belle that the boom
cable broke because it was pinched and so held.
10. According
to the evidence of Mr. Belle, the consultant mechanical engineer
which I accepted, the boom cable is most likely to become
pinched when the cable is coiled back in after extension out
to its limit. Pinching may occur within a drum which is in
the cab of the crane or at the sheaves which are above the
cab and at the end of the boom, but there is a greater risk
of pinching at the sheaves. As Mr. Belle pointed out, during
the exercise of recoiling, in order to see that the cable
does not pinch, it is customary to use two persons although
it is better to have three. Of the two, one operates the controls
and he keeps an eye on the sheave over the top of the cab.
The second person should be at the end of the boom, which
could be anywhere like 30 feet from the cab, checking at that
end. There was no evidence as to the place where the cable
broke nor as to where the pinching occurred.
11. Both
Mr. Holland and Mr. Gibson testified to the extending of the
boom on the day before the accident but while Mr. Holland
recalls seeing the operator Mr. Gibson on the boom during
the exercise, Mr. Gibson is clear that he stayed by the cab.
He said that his assistant one Noel Cannell was inside the
cab. He worked the lever and checked that the cable ran properly
through the sheaves. This meant that the sheaves he was checking
were those by the cab. He also said that when the wire was
coiled in, his assistant Noel Cannell was there watching the
wire coil in. It was his opinion however that the cable can't
be pinched when wire is being coiled back in because there
is a sheaf at the top of the cab which guides wire when it
is being coiled in. He also said it is difficult for him to
say if there would be pinching if there was a hitch in the
sheaf since he had never seen where the sheaf is hitched causing
the cable to pinch.
12. I
found that during the exercise of uncoiling and recoiling
the cable for the purpose of extending the boom two persons
were used, both of whom stayed in the vicinity of the cab.
Mr. Cannell watching the drum and Mr. Gibson working the levers
and watching the sheaves by the cab. I therefore held that
what ought to have been done by the operator to detect pinching
was not done, that is, that a person should have been at the
end of the boom checking the sheaves at that end. Further,
I held that in all probability if the operator had followed
the procedure he ought to have followed, the pinching would
have been detected. This omission amounted to a failure to
take the precaution that was reasonable in the circumstances.
A duty to take that care was owed by the operator to anyone
who would be involved in the use of the crane for the lifting
exercise. I accordingly held that the operator was negligent.
Because of this negligence an undetected pinching of the cable
resulted in its breaking. His employer at the time, the first
defendant, is vicariously liable for his negligence.
13. The
plaintiff was in such a position during the operation for
lifting the bridge that when the boom fell, it struck him.
Mr. Bernier, who was looking after the safety of the persons
helping in the exercise, said that when the bridge was attached
to the crane, he and other persons including the plaintiff
were on both sides of the bridge waiting to see if rebalancing
was necessary when the test lift of the load was made. The
plaintiff was beside him and about 12 feet from the line of
the boom. When the cable broke, he Bernier, heard a noise,
looked up at the boom, saw its reaction of lifting and then
coming down as usually happens if a cable breaks, and he ran.
He did not see what Eric Flowers did. The operator, Mr. Gibson,
said that when he got the signal to lift the bridge, he saw
the plaintiff standing near the tank, about 10' - 15' from
the boom. He engaged the lever, suddenly heard a noise and
saw the boom coming down. It hit the tank in which the bridge
was to be placed. He saw the plaintiff run from where he was
to the right. The boom slid out to the right for about 15
- 20 feet. It hit the plaintiff while he was running. It landed
about 15' - 20' from where the plaintiff was originally standing.
14. Now
Mr. Moguel said that it is important that whenever a crane
is being operated, no person should be allowed to be within
the range within which the boom can circulate. It is also
important that whenever there is need for persons to be around
to do anything concerning the weights to be lifted, there
should be no movement of the boom while anyone is moving in
the area. Mr. Holland said that for the riggers, those persons
who sling the load and assist in rebalancing, the safety rules
are that they should not stand in the vicinity of the load
in case of mishap, never under the boom or the object lifted.
They could stand maybe five to ten feet away. When a test
lift is being done, it is a safe procedure for the riggers
to remove themselves. Mr. Bernier stated that at this particular
exercise, he acted according to normal procedures. According
to him it is normal to stay close to the load in case there
is need to realign it but not underneath the boom. As far
as he recalls he and others were clear of the boom. Lastly
Mr. Belle, looking at the position of the plaintiff at the
time as shown on a plan by the crane operator Mr. Gibson,
that is near the tank, stated that in his opinion that spot
was not a safe place to stand. Further, if he was in charge
of the operation, he would have told him to go somewhere else.
15. I
acted upon the evidence of Mr. Belle and held that the plaintiff
was not in a safe place when the boom fell. I am fortified
in this view by the fact that when the boom was falling, Mr.
Bernier ran - I took this to mean that it would not have been
safe to be in the position he was in, when the boom touched
ground. The plaintiff was close to Mr. Bernier and he also
ran - I concluded for the same reason. To my mind, the plaintiff
was in that place at the time on account of the cavalier manner
in which the operation was carried out. According to the crane
operator, no precautions were taken to see that the men, assisting
on the ground, were clear. This evidently was because the
lifting of the steel bridge of 4 tons in weight was not regarded
as a particularly difficult operation. He said that if the
weight was 30 tons everybody would have taken the precaution
to have everyone clear of the load and the boom. Mr. Bernier,
who was looking after the safety of the people assisting,
can't recall giving any instruction to them to get clear.
Both the crane operator and Mr. Bernier left the impression
that they regarded it as alright for the riggers which included
the plaintiff to be standing as they were at the time. On
the other hand the evidence of Mr. Belle is that the most
vital time in a lifting exercise is when the crane assumes
the load. Once it assumes, it is not dangerous. The inference
then is, that when the crane is about to assume the load,
riggers ought to be clear. I concluded that in the circumstances
the care which ought to have been taken for the safety of
the riggers, which include the plaintiff, was not taken. The
employers of the plaintiff, the second defendant, failed in
their duty to take reasonable care for the safety of the plaintiff.
I accordingly found that the second defendant was guilty of
negligence.
16. The
defendant are jointly and severally liable to the plaintiff
for their negligence. As a result of this accident on the
6th July, 1979 the plaintiff suffered grave injuries. When
admitted to the Belize City Hospital on that day there was
an obvious deformity in the spine at the back and he was totally
lacking in sensation and power throughout both lower limbs
and in the peritonial area at the back. X-rays confirmed a
fracture of the first lumbar vertebrae and a forward displacement
of the spine above that. The doctor's opinion was that the
plaintiff needed an emergency operation for the fracture of
the spine but since facilities for this kind of operation
were not available in Belize, the plaintiff was referred to
a hospital abroad, i.e. the Jackson Memorial Hospital in Miami,
Florida. He was operated on and the bones put back in place
and held in position by the insertion of long metal rods.
The plaintiff remains totally lacking in motor power and sensation
in both lower limbs and is able to propel himself for short
distances with the aid of two crutches and two leg braces.
His bladder and bowel functions are impaired. Because of the
impairment of his bladder function, he is likely to encounter
problems with his urinary tract causing demise at an early
age. For the remainder of his life, the plaintiff will remain
paraplegic with the impairment of his bowel and bladder functions.
For him, sexual intercourse will not be possible. His urinary
system will need to be constantly viewed. When last seen by
the surgeon in Belize on 24th March, 1981, the plaintiff was
very depressed and badly adjusted physically to his situation.
17. The
plaintiff has the use of the upper part of his body and is
capable of tasks involving only the upper limbs provided the
lower part of the body is stationed securely. He can learn
to do this and through rehabilitation learn to live to the
maximum capacity with his body such as it now is.
18. He
used to play basketball and performed in both school and public
competitions. He also played a little football. He can enjoy
these pursuits no longer.
19. The
plaintiff must receive proper compensation in all the circumstances
for his injuries and loss.
20. I
turn now to the question of damages and consider first the
special damage claimed. The plaintiff satisfied the court
that the amounts claimed were reasonably and properly incurred
and flowed from the defendant's negligence. They total $20,345
U.S. or $41,076.04 Bze. and I allow them.
21. In
the assessment of general damages, I kept in mind the several
considerations outlined in Cornilliac v. St. Louis 7 W.I.R.
491. Firstly as to pain, suffering and loss of amenities
I considered awards of general damages in cases of paraplegia,
remembering the words of Lord Morris in Singh v. Toong
Fong Omnibus Co. Ltd. (1964) 3 A.E.R. at p. 927 "to
the extent to which regard should be had to the range of awards
in other cases which are comparable, the cases should as a
rule be those which have been determined in the same jurisdiction
or in a neighbouring locality where similar social, economic
and industrial conditions exist."
22. My
attention was not drawn to any comparable local cases but
I looked at the awards made in two cases adjudicated in Trinidad
and Tobago, (i) Aziz Ahamad Ltd. V. Raghunar Raghubar 12
W.I.R. 352 and (ii) DeSouza v. Trinidad Transport (No.1)
18 W.I.R. 138 affirmed at 25 W.I.R. 511 wherein
some English awards were also looked at. While the awards
in neighbouring territories at the time of those cases appear
to be in the range of $30,000 - $40,000, the English awards
are in the range of £ 25,000.
23. I
made allowance for the fact that it is now 10 years since
the award in the latest case referred to. I am not aware of
an award in this region in a case of paraplegia since then
so I looked also at the following English awards: -
(1) |
Monarty
v. McCarthy (1978) 1 W.L.R. 155 in which the plaintiff,
a woman of 24, sustained back and head injuries as a result
of which she suffered paraplegia. In making his award
of £ 35,000 general damages O'Connor J stated that
"£ 27,500 was the appropriate award for loss
of amenity in case of a man of 24 who in spite of paraplegia
was capable of a range of activity.". |
(2) |
In
Angus v. Jones (1980) C.A. Kempt & Kemp 1-210/1,
the plaintiff, aged 26 at the date of the incident, suffered
fractures of the 5th, 6th & 7th thoracic vertebrae
resulting in complete paraplegia. There was complete loss
of motor function and sensation from mid-chest downwards.
He had no control of bladder or bowel functions and there
was total loss of sexual function. A constant pain just
below the level of loss of sensation which prevented him
from working or concentrating was likely to be permanent.
He would be confined to a wheelchair for the rest of his
life. His bowels had to be evacuated digitally every day
and his bladder operated in a reflex fashion. The plaintiff
was awarded £ 40,000 general damages for pain and
suffering and loss of amenities. |
(3) |
In
Walker v. John Melcan & Sons Ltd. (1979) 1 W.L.R.
760 the trial judge awarded £ 35,000 for pain,
suffering and loss of amenity including loss of expectation
of life and loss of sexual function. Here the plaintiff,
despite his paraplegia, was able to lead a life of his
own, was able to work and had recreations and social life.
His expectation of life had been shortened. On appeal,
(1979) 2 A.E.R 965 at 970 Cumming-Bruce L.J. observed
that this award of £35,000 restored consistency
with awards made under this head before 1973 and should
be regarded as a safer guide to the damages appropriate
in such a case than the award of O'Connor J. in Monarty
v. McCarthy (supra). |
24. In
seeking assistance from a comparison of awards, I kept in
mind the differences in the material facts of respective cases.
I also took into account that there is still an accepted difference
in the level of awards in the U.K. and this region.
25. Guided
by the considerations outlined above, I consider that fair
compensation for pain, suffering and loss of amenities would
be $50,000.00.
26. I
consider now the matter of the loss of pecuniary prospects.
On July 6th, 1979, the plaintiff, then 18 years of age, was
employed as a labourer at a wage of $1.250 per hour. On the
basis of 8 hours per day and 300 work days per year this would
be $3,000 per annum. He had passed three subjects at '0' level
and intended to go to the Technical College to do engineering
course in order to become a building engineer. He would have
required two more passes at '0' level and qualification at
tertiary level before becoming a building engineer but there
was no reason to suggest that he would not have become thus
qualified. The evidence is that a building engineer earns
$250.00 per week or $13,000 per annum. There is evidence however
that a person in the plaintiff's condition once psychologically
rehabilitated, would be able to study as much as he could
before and be employed as a Draftsman. The earnings of a draftsman
is about $130.00 per week or $6,760.00 per annum. I held that
the plaintiff as a result of his injury, has been deprived
of the opportunity to earn eventually wages of $13,000.00
per annum whereas on a balance of probabilities he still may
be able to earn up to $6,760.00 per annum. Having regard to
his prospects and his level of earnings at the date of the
accident I held that the plaintiff was entitled to take into
account in the assessment of damage under this head the loss
of opportunity to earn substantially higher wages.
27. I
assumed that the plaintiff would have had working life up
to age 60 or 41 more years and in calculating this damage
I used his earnings of $3,000.00 per annum as the basis of
my calculations. The multiplier of 41 I scaled down for all
the imponderables including the possibility that for some
period the plaintiff may have been engaged in study without
earning anything and to take into account the fact that a
lump-sum payment is being made and to allow for the uncertainty
of the incidence of income tax. It was readjusted having regard
to what were the plaintiff's prospects in relation to his
level of earnings at the date of the accident. I used a multiplier
of 18 and arrived at a figure of $54,000.
28. I
considered further the question whether the plaintiff should
have an award of future medical care and attention. The evidence
of the surgeon was that the plaintiff will require further
operation to remove rods presently inserted at the spine and
to remove the lumps of calcium which have developed in front
of both hip joints and which if not removed would impede movement
of the hips. It appears that he will also have to go to a
hospital outside of Belize for this purpose. His urinary system
will need to be constantly reviewed and he will have to go
through a period of rehabilitation. I was given no precise
figures on which to have calculations for this purpose but
I think provision ought to be made in this regard. Doing the
best I can I would award the sum of $7,500.00 under this head.
29. As
counselled by Lord Denning M.R. in Fletcher v. Autocar
and Transporters Ltd. (1968) 2 Q.B. 322, in order to determine
whether the plaintiff gets fair compensation in all the circumstances.
I look at the overall figure which come to $152,576. I think
it a fair figure in all the circumstances.
30. Judgment
for the Plaintiff in the sum of $152,576.04. He is to have
his costs, taxed or agreed.
----------OO ---------
|