|
(LIOU
TSONG MING |
PLAINTIFF |
BETWEEN
|
(
(AND
( |
|
|
(YEN
CHEN TSAI |
DEFENDANT
|
Supreme
Court
Action No. 445 of 1996
19th April 2000
Shanks, J.
Mr. E.
A. Marshalleck for the Plaintiff.
Mr. Wilfred Elrington, S.C. for the Defendant.
Building
Contract - Breach of Building contract - Damages for breach
of contract - Determination of appropriate quantum.
J U D G M E N T
-
This
is an unfortunate building dispute between two members
of the Taiwanese Community in Belize. It relates to a
partially completed house which the Defendant agreed to
buy from the Plaintiff in December 1995 for US $75,000.00.
The US $75,000.00 was to include the completion of the
house; and the Defendant also purchased two other lots
at Mile 13 at the same time for $50,000.00 (total price
of $125,000.00). The Plaintiff claims $57,482.00 as a
reasonable sum for additional works he says were requested
by the Defendant. The Defendant says that the "additional
works" were all comprised within the US $75,000.00
and he counterclaims $22,000.00 for costs of rectification
which are necessary and $36,000.00 for rent which he says
he has spent since May, 1996 because he was unable to
move into the house. I have heard evidence, through an
interpreter, from both the Plaintiff and the Defendant
(as well as others) but I am afraid I did not feel I could
rely on the evidence of either of them totally. I will
first set out the chronology as far as I can and then
seek to address the contentious items.
- The
chronology is as follows:-
October,
1994 |
Original
plans drawn up; one storey house contemplated. |
29
December, 1995 |
Written
contract in Chinese between Plaintiff and Defendant.
The contract states that to the Defendant's house,
which is not yet finished, there will be added one
more storey, which is exactly like the living room."
Payments of US $9,500.00 and $45,000.00 made by Defendant. |
30
December, 1995 |
Date
of agreement between Plaintiff and Alexander Daniels,
a contractor, "to complete unfinished building
at an estimated cost of $65,000.00." The Defendant
says this and the later agreement with Daniels are
manufactured. |
3
days later |
Plaintiff
says Defendant asked for additional works and alterations
which are the subject of claim. |
9
January, 1996 |
Date
of agreement with Daniels to "construct an extension
along with alterations
all at an estimated
costs of $65,000.00. |
20
May, 1996 |
US
$35,000.00 paid by Defendant. |
8
June, 1996 |
US
$15,000.00 paid by Defendant. |
June,
1996 |
Revised
plans produced for building as in fact constructed
for Defendant. |
30
June, 1996 |
US
$5,000.00 paid by Defendant. |
29
August, 1996 |
US
$15,000.00 paid by Defendant (total $124,500.00). |
15
September, 1996 |
Home
handed over to Defendant. Plaintiff asks for payment
for extras which results in a major dispute. |
23
October, 1996 |
Proceedings
issued. |
2
April, 1997 |
Statement
of Claim. |
1
October, 1999 |
Default
judgment. |
14
January, 2000 |
Judgment
set aside. |
17
January, 2000 |
Defence
and Counterclaim. |
-
The
Plaintiff's evidence was that three days after the written
agreement of 29 December, 1995 the Defendant requested
an extension of the upper floor beyond the agreed area
of the living room and various other changes, and that
he agreed to pay for the materials and labour for them.
He then entered into the second contract with Mr. Daniels
to carry out these works. He and the Defendant inspected
the house together before handover and there were no complaints
and no claim was made until January 2000. The Defendant
said that the original agreement was that he would pay
US $75,000.00 for a finished house done as he wanted it,
and that he gave the Plaintiff the details of what he
wanted verbally. He was unable to move into the house
in September 1996 because of the defects so that he had
been forced to rent ever since. As I have indicated, I
had difficulty accepting either of those stories in its
entirety. Further, there were real difficulties with the
quantum of the Plaintiff's claim. In evidence, he said
that he had paid for the extra items by paying Mr. Daniels
a total of $22,601.00 for labour between January and July
1996, and by paying $35,989.00 for materials himself between
January and September 1996 and he produced receipts for
all these items. However, there was some doubt as to whether,
in fact, Mr. Daniels had ever been contracted, and it
was the evidence of Mr. Mario Magana that normally Mr.
Liou paid him (Magana), and not Daniels, for labour and
that he (Magana) paid Daniels a small commission for introducing
the work. Perhaps more significantly in relation to quantum,
there was no attempt in the course of Mr. Liou's evidence
to break down the amounts paid, and the individual amounts
claimed in the Statement of Claim appear to be based on
some workings (which are pp 15-26 of the Plaintiff's bundle
of documents) which did not feature in the evidence and
were not explained to me.
-
I
turn to the individual items claimed.
(a)
Extension to upper floor $41,355.00
There is no doubt that the written agreement says that
the upper floor would mirror the living room and that
what was in fact constructed on the upper floor was considerably
larger. I reject the Defendant's evidence that the Plaintiff
agreed to do this for no additional payment. However,
I cannot accept the figure quoted for the work by the
Plaintiff. For one thing, the extension was 438 square
feet and not 572 as the Plaintiff claimed: this is clear
from the plans produced by the Plaintiff himself dated
June 1996. For another, Mr. Marshalleck's submission that
the cost of the extension (which worked out at about $80
per square foot for 572 square feet) was explained by
the high cost of the roofing materials did not add up:
the roof was simply moved up one storey but would have
been required in any event. This is the major item of
claim but unfortunately I have no further guidance as
to what is a reasonable sum for the work. Doing my best
with the material I have, I propose to award the Plaintiff
$20,000.00 as quantum meruit.
(b)
Repair cess pool $2,760.00
Mr. Liou told me that Mr. Yen requested that the cess
pool which had already been constructed on site, partially
above ground, should be re-constructed below ground. Mr.
Yen gave no evidence on this topic but Mr. Lennox Myles,
a builder called on his behalf, gave evidence that a septic
tank below ground would not function in the area where
the house is. It seems to me that since the Plaintiff
took it upon himself to build for the Defendant he cannot
claim for the cost of building a useless item unless the
Defendant had been expressly warned of this, and indeed,
he accepted that he had an obligation to provide "a
good cess pool".
(c)
Construct water tank $2,141.00
Mr. Liou told me that Mr. Yen asked for the existing water
tank to be moved from the north side of the building to
the east side, which was undoubtedly done. Mr. Yen told
me that the tank was moved because the northern boundary
of the lot after sub-division cut through the water tank.
Mr. Kent Morris, the former owner of the land gave evidence
that the original tank had been 12' by 12' and that he
had measured the distance from the building to the northern
boundary as 9' 5", which served to confirm the Defendant's
version of events. Given that evidence and that the onus
must be on the Plaintiff, I reject this claim.
(d)
Water trough $1,264.00
This goes with (c).
(e)
Construct wall $3,520.00
There is no doubt that a wall was constructed between
the kitchen and the dining room on the ground floor, and
that this wall is not shown in the original October 1994
plans. Again, I cannot accept that Mr. Liou agreed to
construct this for no extra sum. Mr. Elrington says that
the cost of the wall is exorbitant, but no evidence was
led from Mr. Myles or anyone else as to the correct sum.
I propose to discount the claim slightly to $3,000.00.
(f)
Extend stairway $2,772.00
The Plaintiff's case was that the original work requested
by the Defendant envisaged an inside staircase but that
he later designed and asked for an outside staircase to
be built. Since the ground floor was actually above ground
this meant that five extra steps had to be constructed
to allow for the outdoor staircase. I was not convinced
by the Plaintiff's evidence that the specification in
relation to the position of the steps would have changed
within three days, and I am not sure this was put to the
Defendant in clear terms. I therefore reject this claim
on the basis that the agreement to build on the upper
floor necessarily involved some steps up, and it is not
clear that it was ever agreed they would be internal steps.
(g)
Extend roof $2,182.00
It seemed to be common ground that the roof was extended
so as to create a 6-foot overhang. Both Mr. Liou and Mr.
Yen stated that the other had decided to extend the roof
for reasons which neither could explain. On this occasion
I prefer the Plaintiff's evidence; I can see no reason
why he would voluntarily have incurred extra expenditure
on the building. But I propose to reduce the claim by
? because Mr. Liou stated in cross-examination that there
was to be a 2-foot overhang in any event, which leaves
about $1,400.00.
(h)
Construct kitchen $1,538.00
There is no doubt that the kitchen constructed for Mr.
Yen was not as shown in the original plans or that the
original version would have been more expensive than Mr.
Yen's Kitchen. It was the Plaintiff's case that the original
kitchen had to be demolished before the new kitchen could
be installed. But Mr. Morris gave evidence, which I accept,
that when he sold the house no kitchen had been installed
and the Plaintiff did not tell me of any work being done
before the contract with Mr. Daniels dated 30 December
1995. I therefore reject the Plaintiff's claim on this
item.
-
The
sum of items (a), (e) and (g) is $24,400.00 which the
Defendant ought to have paid for extras. I turn to his
counterclaim as explained by Mr. Myles by reference to
an estimate he had produced following a recent visit to
the property. Mr. Marshalleck did not challenge any of
the figures in this estimate as figures. Nevertheless,
bearing in mind that the Defendant must satisfy me that
the claimed expenses arise from defects or omissions present
when the building was handed over 3 ½ years ago,
and ignoring the claims which were abandoned (nos. 8,
11, 12, 13, 14 and 20), I accept items 2, 3, 4, 6, 9,
15, 16, 17, 18 and 21 which total $8,350.00. I reject
the claim in relation to the plumbing and heaters (no.1),
which was rather unclear and, after three years, speculative.
The evidence about the missing doors (no.5) was inconclusive.
The need for re-painting (no.7) after 3½ years
does not seem surprising. I do not know what molding trim
(no.10) is supposed to relate to. The evidence was that
the steps and landing (no.19) were actually designed by
the Defendant, so that I do not think he can complain
about them unless they were completely unsuitable as stairs,
which I do not believe they were. The counterclaim for
$36,000.00 for rent I have no hesitation in rejecting
in its entirety. Whatever problems there may have been
with the house cannot possibly justify not moving in for
a period of 3½ years at such a cost. The claim
for expenditure of $35,000.00 was also abandoned.
- The
net figure due to the Plaintiff after taking account of
the counterclaim, which I propose to set off against the
claim, is $16,050.00. There shall be judgment for the Plaintiff
for that sum with interest at 12%.
----------OO----------
|